GMATers- Please note: The following question appears in the PowerPrep program CAT test.
I would like confirmation on the method I used to solve the following question. Since PowerPrep only provides answers, I want to see if the method I used is correct or if I was just lucky.
"Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?"
A) 2
B) 3
C) 4
D) 6
E) 7
Answer is B. Below is the method I used:
If 6 machines work at constant rate (1/x) and take 12 days to complete 1 job, then:
Step 1: Find individual rate of machine
R*T=D
6(1/x)(12)=1 and so rate of 1 machine is 1/72 (translated in english this means 1 machine can do 1/72 of the job in 1 day)
Step 2: Find how many extra machines are necessary to complete job in 8 days
(6/72+x/72)(8)=1
(6+x)/9=1
x=3 or 3 extra machines are necessary.
Is this method legitimate or is there another method that may be wholly applicable to these type of problems? Thanks :D